Justia Connecticut Supreme Court Opinion Summaries

Articles Posted in Construction Law
by
The case involves two plaintiffs, Glen A. Canner and Louis D. Puteri, who separately sued a condominium association, Governors Ridge Association, Inc., alleging that the foundations supporting their respective units were defective. The units, part of a common interest community, were purchased by Canner and Puteri in 2001 and 2002 respectively. The defendant had affirmed its responsibility for any foundation settlement issues. However, despite the units suffering significant, uneven settling and the defendant hiring several companies to investigate potential repairs from 2012 to 2016, no repairs were ultimately made. The plaintiffs commenced their actions in 2016 and 2017, alleging that the defendant had negligently designed and constructed the foundations and had violated its duties under the Common Interest Ownership Act (CIOA) by failing to conduct necessary repairs.The trial court concluded that the CIOA claims were time-barred by the statutory three-year limitation period generally applicable to tort actions. The Appellate Court affirmed the trial court’s judgments, concluding that the limitation period set forth in § 52-577 applied because the claims sounded in tort rather than contract. The Appellate Court also agreed with the trial court’s conclusion that the declaration and bylaws created no duty to repair because the relevant declaration required the defendant to repair only insured common elements, and there was no requirement that the foundations themselves be insured.The Supreme Court of Connecticut held that the Appellate Court properly applied the statute of limitations set forth in § 52-577 to the portion of the CIOA claims seeking recovery for negligence during the course of construction of the foundations. However, the Supreme Court found that the Appellate Court improperly upheld the trial court’s disposition, in favor of the defendant, of the claims that the defendant had violated its contractual duties under the bylaws to maintain, repair or replace common elements when it failed to effectuate repairs to the foundations. The Supreme Court concluded that the claims that the defendant breached its contractual duties imposed under the bylaws by failing to repair the foundations were governed by the six-year limitation period applicable to contract claims in § 52-576. The case was affirmed in part, reversed in part, and remanded for further proceedings. View "Canner v. Governors Ridge Assn., Inc." on Justia Law

by
The Supreme Court affirmed the judgment of the appellate court affirming the judgment of the trial court denying a property owner's motion for summary judgment in the underlying dispute with a contractor arising from a construction project, holding that the trial court correctly denied Defendants' motion for summary judgment.Defendants hired Plaintiff to serve as a general contractor to renovate a home located on Greenwich property. Defendants later terminated their contractual relationship with Plaintiff. Plaintiff served mechanics' liens on Defendants and brought this action to foreclose its lien. Defendants moved for summary judgment, arguing that the trial court was required to give res judicata effect to the findings of the trial court in a prior action between Plaintiff and one of Defendants' subcontractors. The trial court denied Defendants' summary judgment motion, determine that all four required elements of res judicata were not met. The appellate court affirmed. The Supreme Court affirmed, holding that the appellate court did not err in holding that the presumption of privity that the Supreme Court held to apply in Girolametti v. Michael Horton Associates, Inc., 208 A.3d 1223 (Conn. 2019), did not apply to the instant case. View "Strazza Building & Construction, Inc. v. Harris" on Justia Law

by
The Supreme Court affirmed the judgment of the appellate court concluding that the Home Improvement Act (Act), Conn. Gen. Stat. 20-418 et seq., did not apply to work performed by Defendant on Plaintiff's property, holding that Plaintiff's claim under the Act was unavailing.The trial court found in favor of Plaintiff on his claims alleging breach of contract, violations of the Act, and violations of the Connecticut Unfair Trade Practices Act (CUTPA), Conn. Gen. Stat. 42-110a et seq. The trial court ruled in favor of Plaintiff. The appellate court affirmed with respect to the breach of contract count but reversed with respect to the remaining claims, ruling that the work performed by Defendant fell within the new home exception of the Act, and therefore, Plaintiff failed to state a claim under both the Act and CUTPA. The Supreme Court affirmed, holding that the work performed by Defendant fell within the new home exception. View "Winakor v. Savalle" on Justia Law

by
The Supreme Court reversed the judgment of the trial court finding Plaintiffs responsible for failing to complete a project by the parties' agreed-upon deadline and awarding Defendant $335,000 in liquidated damages on its counterclaim, holding that the trial court's pretrial interpretation of various agreements between the parties was erroneous.At issue was which party was responsible for delays in constructing Dunkin Donuts Park in the City of Hartford. Plaintiffs, the project's developer and the design-builder, sued the City claiming breach of contract, and the City counterclaimed for breach of contract. The trial court concluded, as a matter of law, that Plaintiffs controlled the architect and were therefore liable for changes to and mistakes in the ballpark's design. Thereafter, the jury found Plaintiffs responsible for failing to complete the stadium by the agreed-upon deadline. The Supreme Court reversed, holding that the parties' contracts did not unambiguously grant Plaintiffs legal control of the architect and the stadium's design across all relevant time periods. View "Centerplan Construction Co. v. Hartford" on Justia Law

by
In this construction dispute between a property owner and a general contractor the Supreme Court affirmed the judgment of the appellate court that, in the absence of clear evidence of contrary intent by the parties, subcontractors are presumptively in privity with the general contractor for purposes of res judicata as to the subcontractors' claims that did not participate in arbitration.These appeals arose from disputes regarding the construction of a store expansion. Plaintiffs, the store owners, and the general contractor, pursuant to a contract between them, entered arbitration to resolve various disputes regarding the project. None of the five subcontractors (Defendants) were formally a party to the arbitration. The arbitrator issued an award ordering Plaintiffs to pay the general contractor $508,597 for sums due. Plaintiffs subsequently filed suit seeking to recover from Defendants. Defendants moved for summary judgment based on res judicata. The trial court denied the motions on the grounds that Defendants were not parties to the arbitration and were not in privity with the general contractor. The appellate court reversed. The Supreme Court affirmed, holding that Defendants were in privity with the general contractor for purposes of res judicata and that Plaintiffs' claims were barred because they could have been raising during the arbitration. View "Girolametti v. Michael Horton Associates, Inc." on Justia Law

by
Contractor and Homeowner entered into an agreement whereby Contractor agreed to furnish materials and supply labor in connection with renovations to Homeowner’s residence. After the renovation project was largely complete, the parties began to dispute the amounts that Homeowner owed Contractor. Contractor then brought this action claiming, inter alia, breach of contract and unjust enrichment. Homeowner raised the special defense that Contractor’s claims were barred because the agreement did not comply with the Home Improvement Act. In response, Contractor argued that Homeowner was precluded from relying on the Act because his refusal to pay Contractor was in bad faith. The trial court agreed with Contractor and rendered judgment for Contractor. The Appellate Court affirmed. The Supreme Court reversed, holding that Homeowner did not act in bad faith, and therefore, the trial court improperly found that Homeowner was barred from invoking the protection of the Act. Remanded with direction to render judgment for Homeowner. View "Burns v. Adler" on Justia Law

by
John and Jane Couto entered into a contract with Joseph General Contracting, Inc. for the purchase and construction of a home and carriage house. The trial court found that the contract existed also between the Coutos and Anthony Silvestri, the owner and president of Joseph General. After disputes arose regarding the construction of the dwellings, Joseph General sued the Coutos for, inter alia, breach of contract. The Coutos counterclaimed against Joseph General, Silvestri and Landel Realty, LLC. The trial court held Joseph General, Landel and Silvestri each jointly and severally liable for breach of contract and implied warranty, trespass and violation of the Connecticut Unfair Trade Practices Act (CUTPA). Silvestri appealed the propriety of these adverse rulings with respect to his personal liability. The Appellate Court affirmed the judgment pertaining to Silvestri in an individual capacity. The Supreme Court reversed the judgment of the Appellate Court as to the claims of breach and contract and implied warranty against Silvestri in his individual capacity and affirmed in all other respects, holding that the Appellate Court (1) erred in determining that Silvestri had incurred contractual obligations to the Coutos in his individual capacity; and (2) properly determined that Silvestri could be held individually liable for alleged violations of CUTPA. View "Joseph Gen. Contracting, Inc. v. Couto" on Justia Law

by
Plaintiff entered into a subcontract with a general contractor to perform work on a public construction project. The general contractor provided a payment bond with Defendant, a surety on the project. Plaintiff later submitted to the general contractor a request for equitable adjustment to the subcontract to recoup additional costs allegedly incurred as a result of the general contractor’s deficient performance. When the general contractor did not respond to the claims, Plaintiff sent Defendant notice of its claim. Defendant failed either to pay or to deny notice of the claim within ninety days as required by Conn. Gen. Stat. 49-42(a). Plaintiff subsequently sued Defendant in federal district court, alleging that Defendant had waived any substantive defenses, and Plaintiff was therefore entitled to judgment in the full amount of the claim. The district court certified questions of law to the Supreme Court regarding the correct interpretation of section 49-42(a). The Supreme Court answered that a surety’s failure to pay or deny a claim under section 49-42(a) within the ninety day deadline is tantamount to a denial of the claim and does not constitute a waiver of the surety’s right to defend the claim on the merits. View "Elec. Contractors, Inc. v. Ins. Co. of State of Penn." on Justia Law

Posted in: Construction Law
by
Plaintiff contracted with the Town of Bethel to perform electrical work in connection with the Town’s renovation of its high school. Plaintiff later sued the Town, alleging breach of contract and unjust enrichment and claiming that the Town must reimburse it for additional costs incurred due to the Town’s ongoing asbestos abatement work at the school. The trial court rendered judgment for the Town in part, concluding that the Town's conduct did not fall within either of two judicial created exceptions to the enforcement of “no damages for delay” clauses adopted by the Court in White Oak Corp. v. Dep’t of Transportation. The Supreme Court affirmed the trial court’s decision that Plaintiff was not entitled to compensation under any of the “no damages for delay” exceptions at issue, holding (1) the term “active interference,” as used in the contract, did not require a showing of bad faith or gross negligence; but (2) the Town’s conduct in this case did not rise to the level of active interference or fall within either of the White Oak exceptions. View "C & H Elec., Inc. v. Town of Bethel" on Justia Law

by
Plaintiffs served as the general contractor and the project developer for construction of a student housing complex at the University of Connecticut (UConn). UConn procured a commercial general liability (CGL) policy for the project, which insured Plaintiffs and their work. Defendant, American Motorists Insurance Company (AMICO), was the issuing insurer's successor in interest. UConn alleged that Plaintiffs breached the agreement with UConn, and Plaintiffs demanded that AMICO defend against UConn's claims. AMICO denied coverage. Plaintiffs settled their claims with UConn and then brought this action against Defendant for breach of contract and bad faith. The U.S. district court certified three questions of law for the Connecticut Supreme Court's consideration. The Court answered (1) allegations of unintended defective construction work by a subcontractor that damages nondefective property may trigger coverage under a CGL policy; (2) under the plain language of the insurance policy in this case, there is no cause of action based on AMICO's failure to conduct a discretionary investigation of claims for coverage; and (3) in global settlements encompassing multiple claims, the insured has the burden of proving that a pre-suit settlement is reasonable in proportion to claims that the insurer has a duty to defend. View "Capstone Bldg. Corp. v. Am. Motorists Ins. Co." on Justia Law